Ultimate guide to extending your home

Ultimate guide to extending your home

From costing and designing extensions to permitted development and building regulations, find out everything you need to know here.

 

 extensions to a 1950s bungalow

 

How much will an extension cost?

You’ll need to allow around £1,500 per square metre for the building work — and, for higher specification finishes, up to £3,000 per square metre. If you’re adding bi-fold doors, allow £1,400 to £1,800 per metre for these. Bear in mind that small extensions (under 15–20 square metres) have higher costs per square metre, and that clay, peat, lots of nearby trees, or sloping ground will increase foundation costs.
‘As a very rough rule of thumb, costs should be split into 50 per cent for construction and 50 per cent for the interior,’ says Hugo Tugman, founder of Architect Your Home and Interior Your Home. ‘If you do not want to compromise on the size of what you are building, you may be able to make considerable savings on interior finishes.

skandinavian style kitchen extensions in london


This Scandinavian style kitchen extension in London cost less than £70k,

For example, tiles can range from £15 to £150 per square metre; timber flooring from £30 to £300. The more expensive options are generally much better quality and more beautiful, but therein lies the compromise in meeting your budget.
It is important that you get quotes from at least four builders. It is almost certain that each of the builders will provide different costs for exactly the same work using the same materials. If you only approach one or two builders, you run the risk of only obtaining high quotes, rather than getting an idea of an average.

Click here to get a comprehensive extension cost calculation using our free extension cost calculator

Planning permission and permitted development for extensions

How to extend without planning permission

‘Homeowners are sometimes surprised at how much can be built on to a house under permitted development rights,’ says Alan Cronshaw of Acronym Architecture & Design. Even in Conservation Areas you can build rear extensions as long as they meet the size criteria and are in matching materials.
If you are planning to build an extension under permitted development rights, study the criteria carefully and apply for a certificate of lawful development from your local authority. This only costs £86, and you will then have the paperwork in place to prove that your extension did not require planning permission.
industrial style glazed kithcen extensions

This industrial-style glazed kitchen extension took two years to get planning permission,

When you will need planning permission for your extension

The cost of a planning application is £172, an expenditure that you don’t want to have to make several times. Make sure you have gone through your plans thoroughly with an architect or builder that is familiar with the local planning council and their preferences.
When building a more ambitious extension you will need planning permission if:
  • Your extension covers half the area of land surrounding your home
  • If you are extending towards a road
  • You are increasing the overall height of the building
  • You are extending more than six meters from the rear of a semi-detached house*
  • You are extending more than eight meters from the rear of a detached house*
  • Your single storey extension is taller than four meters
  • Your single storey extension is to the side of the property and more than half the width of your house
  • You are using materials that differ from the original style of the house
  • You plan on building a balcony or raised veranda
For more detail on when you will need planning permission, visit the Planning Portal
*For a period of six years, between 30 May 2013 and 30 May 2019 – householders will be able to build larger single-storey rear extensions under permitted development.

What to do if a planning application is rejected

‘First, it’s important to try to understand exactly why the application was rejected,’ says Hugo Tugman. ‘The proposals may be largely acceptable, but simply contain a detail that the local authority can’t approve, in which case resubmitting a new application that has been amended accordingly should be enough to get the permission that you require.
‘It may, however, be that what you are proposing is fundamentally outside the planning policy or guidance the planners are working with. If that is the case, you really need to understand what these policies are and redesign so that your scheme falls within these parameters.
‘The third possibility is that you feel your scheme was within the policy guidance, but the planning department has made an unreasonable interpretation of the rules and refused it. In this final case it may well be worth going to an appeal, where an inspector (not local authority) makes an independent assessment of whether policy has been applied correctly and reasonably.’

Changing your extension design

Changing your extension design after your planning application has been accepted will require a retrospective amendment, or a new application all together. The key to avoiding this situation is to study your plans in detail and have a physical or digital model created to help with visualization.
country traditional style extensions
Annabelle and Jack Diggle had to navigate a particularly strict planning office to get this traditional, pitched roof extension,
‘Occasionally, situational developments may mean that changes are unavoidable and retrospective amendments sound like a good idea. However, in recent years planning departments have been less ready to go down this path.’ says Hugo.
‘If the changes are very slight, it is indeed possible to apply for a “non-material amendment”, but changes that may affect anything significant, such as the overall height or positioning of upstairs windows, would be “material”, and the planners would have to advertise all over again, so they generally push you down the route of a new application.’



Single storey extensions and two storey extensions

‘You are far more likely to get planning permission for a one-storey extension than one with two floors,’ says Hugo. ‘If you can get two storeys approved, there are definite cost benefits, because you will be getting twice as many square metres of additional space in your home for considerably less than double the cost of a single storey.
Single storey extensions are often about enlarging an open space like a kitchen-diner, allowing daylight to flood in through roof glazing and for it to be more informal. However, first-floor spaces are usually bedrooms and bathrooms, and adding an extension to the rear of a first floor can create awkward spaces, leaving rooms in the middle with no daylight and requiring wasteful areas of corridor.
‘They can also restrict the amount of daylight that a single-storey extension can bring into the heart of the ground floor. Such problems, however, are usually solvable when a skilled professional designer helps to work out the floorplan.’

Side extensions

In many cases, two-storey side extensions should not be a problem, but it’s a good idea to discuss your proposals with the planners before spending money on drawing up detailed plans, especially if you are extending over two storeys. They will consider:

Footprint

There are few limits on the size of your extension’s floor area unless it’s likely to cover more than half the garden (including any existing extensions and outbuildings).

Height

You’re not normally allowed to build higher than the existing house. However, side-extension roofs and walls often need to be set back slightly from it (perhaps by 10–15cm).

Overlooking

Features such as upper-floor balconies can be contentious if they overlook the neighbours. For windows, you can use obscure frosted glass, install them at a high level, or fit skylights.

Overshadowing

Building a two-storey, or higher, extension too far out from the back of the house into your garden may overshadow the neighbours, which will limit the permissible size.

Highways

If your proposed extension could interfere with visibility for motorists, it will also limit how far out you can build.
‘Another factor to bear in mind when building within three metres (or in some cases, six metres) of neighbouring buildings is the Party Wall etc Act, which requires you to formally notify the adjoining owners two months in advance of the proposed project.’ Says Ian Rock.

Matching your extension with your existing home

‘There is no hard-and-fast rule on what materials will be accepted by the planning office. It depends on the building, the area, local planning policy, and you — the homeowner,’ says Hugo Tugman.
‘It used to be that planners generally wanted extensions to be in keeping with the original building, which led to a rash of pastiche additions to older buildings, but these days there is more and more of a prevailing view that allowing an original building to be itself.
kitchen extensions exterior
This single storey, innovative extension is clad in a blue render, and cost less than £100k,
‘Contrast does not have to mean shiny modern or hi-tech. It is generally a good idea when extending an old building for the extension to play a quieter role to that of the original building, and it is quite possible to produce a relatively contemporary design that is modest and calm in its expression.’

How to create an open plan space

‘Open-plan or, more frequently, semi-open-plan living, is very popular, as it suits most people’s modern lifestyle and enhances the sense and use of space within the home,’ says Hugo Tugman. ‘I do generally encourage people to go this way; however, there are a number of things to bear in mind when working out how best to use the space.
‘It’s usually a good idea to identify different zones within your layout — such as the kitchen, dining and living areas. The look and feel of your space can be fine-tuned by the extent to which the boundaries of these are defined or blurred, and there are lots of devices, such as continuing through or changing the floor finish, for example, which can control this degree of separation.
‘While walls can block up an open space, they can be helpful when it comes to positioning furniture, storage and radiators, for example. One of the reasons that underfloor heating works so well in an open-plan space is because often there are not enough suitable walls on which to position radiators.’

Extensions with bi-fold doors

‘There is a range of different options available for bi-fold doors, from two-door models through to large eight-door configurations, set-ups for bay arrangements and entire 90-degree corner sections,’ explains Neil Ginger, CEO at Origin. ‘The price of bi-fold doors varies but, as a guide, a bespoke, aluminium design would cost from £1,200 per door leaf.
‘The space allowance for the doors to open outside depends entirely on their width. Bi-fold doors can be as narrow as 40cm, protruding less than half a metre outwards, while you will need to allow just over a metre of space for doors with a width of 1.2 metres.
‘Doors that open inwards are ideal for projects where space outside is limited — on a balcony, for example. In the majority of cases, it is recommended that outward-opening doors are chosen to prevent any rainwater from coming into the home when the doors are opened after it’s been raining.’
Bi-fold doors can also be installed internally, as the low threshold of the design can create a seamless transition from one room to another.’

Building regulations for extensions

‘All home extensions need to comply with the building regulations,’ says Ian Rock. ‘Most obviously, this relates to structural stability — including foundations, window and door openings, lintels, beams and roof structures. Therefore, your design will normally need to incorporate a structural engineer’s calculations, submitted together with drawings as part of your building regulations application.
‘When it comes to submitting your application, you can either do this via local authority building control, or an independent firm of approved inspectors. Either way, there are two ways of making an application — either “full plans”, or the short-cut method known as a building notice.
For a major project such as an extension, it makes sense to get your design approved with the former before you start work, otherwise you could run into trouble if your project doesn’t comply with the regulations.
industrial style kitchen extensions in london

This industrial kitchen extension cost less then £100k and is flooded with light by a series of roof lights.
‘When work is due to start, it is essential to liaise regularly with building control, as they will need to carry out site inspections at key stages, commencing with start on site and excavation of foundations. Finally, once your new extension is built, don’t forget to obtain proof of compliance in the form of a completion certificate — this is a key document when you come to sell.’

What to submit to make sure you comply with building regulations

For all applications:
  • Completed Building Notice form
  • a plan to a scale of 1:1250 minimum showing the location, boundaries, drainage and sewers
  • the appropriate fee
For a Full Plans application*:
  • Completed application form
  • estimate of costs
  • the appropriate fee
  • two copies of detailed drawings at a scale of 1:100 minimum
  • two copies of a site plan showing the proposal, site boundaries and sewer positions
  • two copies of any plans and specification to accompany drawings including structural design and calculations
  • four copies of plans for buildings covered by fire safety legislation, showing fire resistance, fire detection, alarms, emergency lighting, means of escape and signage
*If online applications are accepted, only a single copy of each plan is required.

Fireproofing a new extension

Most extensions should naturally comply with fire regulations thanks to the inert qualities of building materials such as plasterboard, bricks and concrete blocks, which can normally resist the spread of fire for at least 30 minutes,’ says Ian.
However, where you have any exposed major structural components such as timber posts and steel beams, they will normally need to be protected, for example with skimmed plasterboard lining. Also, where holes are cut in ceilings for recessed lighting, they may need to be fitted with fire hoods. Extensions built with modern timber-frame wall panels are lined internally with inert plasterboard and also incorporate integral cavity barriers to slow the passage of smoke and fire.
If your design includes an integral garage, then the walls and ceilings need to resist fire — which most materials should manage, although special pink- coloured plasterboard (fireboard) is the ideal cladding for ceilings and stud walls. Ceilings to integral garages must be plastered, and any doors from the house must be fire doors with a suitable step down into the garage (normally 10cm).
Requirements become a lot more demanding for extensions of three storeys or more. Considered as part of the newly enlarged house, this might involve fitting special fire doors to all new and existing rooms as well as ensuring there is a safe escape corridor (usually via the landing and stairs) down to a main exit door, with the stairs protected with a fireproof lining.
‘If your extension is two storeys or higher, it is best to assume that you need to fit a mains-operated smoke alarm to the upstairs landing(s) in the newly extended house.’

Where to begin your extension

Building materials

  • BRE
    Expert advice from building research professionals
  • GreenSpec
    Green-building resource with directory of materials for sustainable construction
  • Self Build
    Site produced by Travis Perkins with links to materials suppliers
  • SPAB
    Guidance on historic building materials from the Society for the Protection of Ancient Buildings

Decorating

Expert advice

  • Homebuilding & Renovating magazine
    Information, inspiration and source books for improvements, including extending
  • RICS
    Guides on extending, party walls and right to light from the Royal Institution of Chartered Surveyors

Planning information

Professionals


 

Friday, 19 May 2017

Creating Plans for Buildings Regulations


  Creating Plans for Buildings Regulations


 

Chartered surveyor Ian Rock bravely gets to grips with the task of creating his own Building Regulations compliant drawings — a task that takes him five days of ‘study exile’

Last month, my wife Ewa and I found ourselves in a bit of a quandary while preparing plans for our new extension. I was keen to try my hand at preparing the detailed drawings for our Building Regulations’ application, but with professional CAD packages costing well into four figures, the sums simply didn’t add up.

Rear elevation of Ian Rock's proposed extension
Factor in the cost of your own time, and it makes a lot more sense to appoint a professional to do the job for you. But in this instance, I was determined to learn a new skill and prepare my own drawings.
After more research, my hopes were raised when I came across a possible solution — Arcon’s 3D Architect Designer software looked like it might fit the bill, with a range of packages priced from £150 to £550. After speaking to Tim Bates at Elecosoft (the company behind the software), I took the plunge and opted for Arcon Evo, a well-reviewed CAD package specifically geared to ‘building design and floorplans’.
After five days of self-imposed ‘study exile’ I emerged pale and blinking into the daylight, proudly clutching a set of professional-looking drawings. My efforts were greatly assisted by the facility to import existing scale drawings and trace over them using guidelines, thereby ensuring continuity with the planning drawings.

Creating Detailed Drawings

To my great satisfaction, it was now possible to print out multiple copies whenever required. Although the same result could have been accomplished in a fraction of the time by drawing plans by hand, the real bonus comes if you need to make any amendments, produce working drawings for the builders, or produce more detailed drawings of specific areas, such as foundations or floor joists, using an earlier copy as a template.
To avoid cramming all the details on one A1- or A2-sized sheet, I submitted the following additional information on separate documents:

Thermal insulation compliance

This lists the U values you aim to achieve for each thermal element of the building — the walls, roofs, windows, doors and floors. The performance obviously depends on the choice of construction materials and how easily heat passes through them (the ‘lambda-value’ or ‘K-value’) as well as the type and thickness of the insulation. Fortunately, there are plenty of online calculators available, such as the one on Kingspan Insulation’s website.

Span tables

The span and spacing of floor joists, roof rafters and flat roof joists will normally be calculated by your structural engineer, although there are span tables online that you can view for reference (try rightsurvey.co.uk/joist-span-tables-for-floor-construction). Alternatively, if you provide the manufacturers of I-joists and beam and block floors with your drawings, they should be able to provide the necessary calculations free of charge.

Window-to-floor ratio

The combined area of all new glazing in an extension (e.g. windows, doors and rooflights) should total no more than 25% of the internal floor area (after deducting any existing openings covered over by the extension from the total area of new glazing). The proposed total area of new glazing on our extension, at 35m2, far exceeds the 28m2 allowed to us under the ‘25% rule’ (based on 112m2 gross internal floor area).
Happily, factoring in the total area of existing windows and doors engulfed by the extension buys us an additional 7m2 — just enough to comply! Where your design exceeds this, you will need to provide some form of justification, usually achievable by beefing up thermal efficiency elsewhere in an extension.

Time-Saving Measures

The job of the drawings is to tell building control in diagram and text form how each specific part of the building is going to comply with the Buildings Regulations. But no matter how much of a CAD genius you are, there’s no point trying to illustrate complex design details that already exist in diagrammatic form. Fortunately, Arcon programs can import ‘ready-made’ detailing.
There is an excellent website for this purpose, BuildingRegs4Plans.co.uk, where, for a small fee, you can download a wide selection of diagrams and incorporate them in your plans. This saves you having to scour through the Approved Documents (the Department for Communities and Local Government’s hefty guidance on ways to meet Buildings Regs) to try and locate relevant diagrams. You also get access to a lot of useful Building Regs compliance text which can be copied and pasted to populate your drawings (and edited if required).
In the end, our completed application comprised a set of 16 A3-sized drawings (mostly 1:100 scale). In addition to those showing the main elevations, floorplans, sections and site layout, it was a simple job to print off additional sheets with details of drainage, ventilation and floor structures — thanks largely to the availability of ready-made diagrams and pre-formulated chunks of text.

Submitting Plans to Building Control

In my local authority, the fee payable for a Full Plans application depends on the projected floor size. As it was, we ended up with a total bill of £880, comprising an initial £320 charge payable up front, with the balance paid as an ‘inspection charge’ around the time of the first site visit. The alternative Building Notice route is now 20% more expensive, presumably in a bid to put people off using the ‘short cut’ method.
There was just one key document left outstanding, probably the most important of all — the structural engineer’s calculations. However, before our drawings could be completed there were a couple of structural issues I first needed to get some advice on. My next task was to find a tame structural engineer…

 

Ian's-proposed-elevations-created-in-his-CAD-software

 

The-proposed-drainage-plans-for-the-ground-floor

 

The-proposed-drainage-plans-for-the-ground-floor
The proposed drainage plans for the ground floor of his extension